Jasmine Street connects with Okoma Drive (State Route 215) just south of the proposed project vicinity. The roadway serves several businesses, the hospital, and a school athletic facility. The roadway was recently reviewed by TIB staff and received a PCR of 50. The roadway has medium alligator cracking ranging from 13% - 24%. It lacks sidewalks, and adequate storm drainage. Access along the roadway is largely not controlled by formalized approaches
Projects — TIB Project Information
TIB Project Information
City of Omak's Jasmine Street
6-E-987(006)-1
6-E-987(006)-1
Jasmine Street
Haussler Rd to 6th Ave W
FY 2019 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $678,138
County: Okanogan | Legislative District: 7 | Project Length: 0.42 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/02/2020
Project Information
| Lead Agency | OMAK |
| Funding Year | 2019 |
| Program | SCAP |
| Current Phase | Audit |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.42 mi. |
| ADT | 2,000 |
| Functional Class | TIB Arterial |
| Type of Work | Reconstruction |
| Project Contact | Ken Mears |
| Contact Email | publicworks@omakcity.com |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 11/02/2020 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/17/2017 | |
| Delayed Project Date | 07/01/2020 | |
| DAHP Assessment Date | 04/02/2019 | |
| Predesign Approval | ||
| Design Approval | 01/01/2018 | 02/08/2018 |
| Bid Auth. Approval | 03/01/2020 | 02/19/2020 |
| Construction Approval | 04/01/2020 | 05/05/2020 |
| Project Closeout | 12/31/2020 | 10/19/2020 |
| Audit Date | 11/02/2020 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 80,460 | 89,387 |
| Right of Way | 0 | 0 |
| Total Design | 80,460 | 89,387 |
| Construction Engineering | 80,460 | 86,330 |
| Construction Contract | 536,580 | 577,770 |
| Other Construction | 0 | 0 |
| Total Construction | 617,040 | 664,100 |
| Funding Surplus | - 19,362 | |
| Total TIB Funding | 678,138 | 753,487 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| OMAK | 75,349 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 75,349 | 10.0% |
Project Description
The project pulverizes the existing roadway adding cement treated base if necessary. The scope includes installation of curb and gutter on both sides of the street with storm drainage facilities. To extend the pedestrian walkway, the city plans sidewalk on one side of the street.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||