Due to heavy vehicle traffic, street cuts and years of general deterioration, Main Street, one block of Preston Ave and one block of W 2nd St have become heavily cracked and in need of an overlay.
Projects — TIB Project Information
TIB Project Information
City of Waitsburg's Main Street Overlay
6-E-938(008)-1
6-E-938(008)-1
Main Street Overlay
Preston Ave 3rd St to 1st St
FY 2027 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $100,000
County: Walla Walla | Legislative District: 16 | Project Length: 0.50 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
| Lead Agency | WAITSBURG |
| Funding Year | 2027 |
| Program | SCAP |
| Current Phase | Design |
| Legislative District | 16 |
| Congressional District | 5 |
| Federal Route Number | 0124 |
| Project Length | 0.50 mi. |
| ADT | 356 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Randy Hinchliffe |
| Contact Email | administrator@cityofwaitsburg.com |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | |
| Cultural Resource Assessment | Section 106 |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 03/01/2026 | 03/19/2026 |
| Bid Auth. Approval | 02/01/2027 | |
| Construction Approval | 03/01/2027 | |
| Project Closeout | 12/31/2027 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 10,075 | 75,000 |
| Right of Way | 13,434 | 100,000 |
| Total Design | 23,509 | 175,000 |
| Construction Engineering | 10,075 | 75,000 |
| Construction Contract | 65,073 | 484,400 |
| Other Construction | 1,343 | 10,000 |
| Total Construction | 76,491 | 569,400 |
| Total TIB Funding | 100,000 | 744,400 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| WAITSBURG | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| WSDOT | 200,000 | 26.9% |
| WSDOT | 444,400 | 59.7% |
| Total Local Funding | 644,400 | 86.6% |
Project Description
2' grind and overlay.
Existing Condition
Project Benefits
- Improves arterial network;
- Restores structural condition
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||