The roadway is in poor condition and lacks pedestrian facilities which results in pedestrians having limited access from this side of the town.
Projects — TIB Project Information
TIB Project Information
City of Goldendale's Darland Drive Reconstruction
6-E-935(010)-1
6-E-935(010)-1
Darland Drive Reconstruction
Railroad Ave to Mill St
FY 2026 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $916,989
County: Klickitat | Legislative District: 14 | Project Length: 0.42 | TIB Engineer: Jonathan Heusman | Last Payment Date: 04/02/2026
Project Information
| Lead Agency | GOLDENDALE |
| Funding Year | 2026 |
| Program | SCAP |
| Current Phase | Construction |
| Legislative District | 14 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.42 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Reconstruction |
| Project Contact | Sandy Wells |
| Contact Email | swells@ci.goldendale.wa.us |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 04/02/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | 04/11/2025 | |
| Predesign Approval | ||
| Design Approval | 12/31/2024 | 01/07/2025 |
| Bid Auth. Approval | 03/04/2025 | 04/21/2025 |
| Construction Approval | 05/15/2025 | 05/29/2025 |
| Project Closeout | 06/30/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 93,266 | 77,220 |
| Right of Way | 0 | 0 |
| Total Design | 93,266 | 77,220 |
| Construction Engineering | 93,266 | 122,220 |
| Construction Contract | 777,221 | 819,436 |
| Other Construction | 0 | 0 |
| Total Construction | 870,487 | 941,656 |
| Funding Surplus | - 46,764 | |
| Total TIB Funding | 916,989 | 1,018,876 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| GOLDENDALE | 101,887 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 101,887 | 10.0% |
Project Description
Project will add sidewalk and compliant ADA ramps as well as reconstruct the roadway.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||