North 2nd Street is a main arterial that connects the residential portion of Coulee City to US-2, the primary travel route through the region. The current elevations on N 2nd St create areas of extreme cross slopes that make for poor winter driving conditions. The road superelevation is between 8 and 13 percent. Storm water ponding occurs at multiple locations along the road edge, leading to further deterioration and dangerous surfaces during freezing conditions. The existing storm water culvert near the intersection is also deteriorating. There are currently no pedestrian facilities provided along 2nd Street to connect the town to the Coulee City Campground, and there is no access control at the Banks Lake Brew/gas station.
Projects — TIB Project Information
TIB Project Information
Town of Coulee City's 2nd Street Reconstruction
6-E-856(004)-1
6-E-856(004)-1
2nd Street Reconstruction
Washington St to US 2
FY 2027 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $1,280,300
County: Grant | Legislative District: 13 | Project Length: 0.25 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
| Lead Agency | COULEE CITY |
| Funding Year | 2027 |
| Program | SCAP |
| Current Phase | Design |
| Legislative District | 13 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.25 mi. |
| ADT | 750 |
| Functional Class | TIB Arterial |
| Type of Work | Reconstruction |
| Project Contact | Natalie Garrett |
| Contact Email | tcoulee@odessaoffice.com |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 04/01/2026 | 01/21/2026 |
| Bid Auth. Approval | 01/30/2027 | |
| Construction Approval | 03/15/2027 | |
| Project Closeout | 10/31/2027 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 147,700 | 147,700 |
| Right of Way | 0 | 0 |
| Total Design | 147,700 | 147,700 |
| Construction Engineering | 147,700 | 147,700 |
| Construction Contract | 984,900 | 984,900 |
| Other Construction | 0 | 0 |
| Total Construction | 1,132,600 | 1,132,600 |
| Total TIB Funding | 1,280,300 | 1,280,300 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| COULEE CITY | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
The project will pulverize, regrade, cement treat the existing base, and repave 2nd Street. A new curb will be added to both sides of the road with storm drainage facilities, including a culvert. Sidewalk will be added to one side to provide a safe separation for pedestrians and connections to places. Crossing improvements will be made to the intersection of US-2 and 2nd Street.
Existing Condition
Project Benefits
- Pedestrian and motor vehicle safety, mobility and access.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||