Davidson Avenue is in moderate condition with alligator cracking throughout. The City previously crack-sealed this road in 2023, however, the current conditions do not make it a good candidate for that. PCR 52
Projects — TIB Project Information
TIB Project Information
City of Woodland's 2026 Overlay
3-W-954(005)-1
3-W-954(005)-1
2026 Overlay
BNSF Railroad to Goering St
FY 2027 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $715,297
County: Cowlitz/Clark | Legislative District: 20 | Project Length: 0.38 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | WOODLAND |
| Funding Year | 2027 |
| Program | APP |
| Current Phase | Design |
| Legislative District | 20 |
| Congressional District | 3 |
| Federal Route Number | 6879 |
| Project Length | 0.38 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Riley Bunnell |
| Contact Email | rbunnell@ci.woodland.wa.us |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/06/2026 | 12/18/2025 |
| Bid Auth. Approval | 05/15/2026 | |
| Construction Approval | 06/02/2026 | |
| Project Closeout | 09/21/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 82,534 | 97,099 |
| Right of Way | 0 | 0 |
| Total Design | 82,534 | 97,099 |
| Construction Engineering | 82,534 | 97,099 |
| Construction Contract | 550,229 | 647,328 |
| Other Construction | 0 | 0 |
| Total Construction | 632,763 | 744,427 |
| Total TIB Funding | 715,297 | 841,526 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| WOODLAND | 126,229 | 15.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 126,229 | 15.0% |
Project Description
2 inch grind and overlay
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||