Kelso Dr. contains one lane in each direction with a center median, has no curb, gutter, or sidewalk. Pavement condition on the shoulders outside of the travel lanes is good and will receive a fog seal treatment only.
Projects — TIB Project Information
TIB Project Information
City of Kelso's Kelso Drive Overlay
3-W-188(006)-1
3-W-188(006)-1
Kelso Drive Overlay
Haussler Rd to Coweeman River Bridge
FY 2027 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $276,663
County: Cowlitz | Legislative District: 19 | Project Length: 0.67 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | KELSO |
| Funding Year | 2027 |
| Program | APP |
| Current Phase | Construction |
| Legislative District | 19 |
| Congressional District | 3 |
| Federal Route Number | 6749 |
| Project Length | 0.67 mi. |
| ADT | 3,070 |
| Functional Class | Minor |
| Type of Work | Resurfacing |
| Project Contact | Craig Bozarth |
| Contact Email | cbozarth@kelso.gov |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 12/01/2025 | 12/02/2025 |
| Bid Auth. Approval | 04/01/2026 | 02/26/2026 |
| Construction Approval | 03/31/2026 | 04/01/2026 |
| Project Closeout | 10/01/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 25,500 | 20,000 |
| Right of Way | 0 | 0 |
| Total Design | 25,500 | 20,000 |
| Construction Engineering | 17,000 | 24,500 |
| Construction Contract | 511,015 | 299,786 |
| Other Construction | 0 | 0 |
| Total Construction | 528,015 | 324,286 |
| Funding Surplus | - 276,852 | |
| Total TIB Funding | 276,663 | 344,286 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| KELSO | 67,623 | 19.6% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 67,623 | 19.6% |
Project Description
2 inch grind and overlay
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||