City of North Bend's 2025 Overlay
3-P-804(008)-1
3-P-804(008)-1
2025 Overlay
Multiple Locations
FY 2027 Arterial Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $744,252
County: King | Legislative District: 12 | Project Length: 1.28 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
| Lead Agency | NORTH BEND |
| Funding Year | 2027 |
| Program | APP |
| Current Phase | Bid Authorization |
| Legislative District | 12 |
| Congressional District | 8 |
| Federal Route Number | 2827 |
| Project Length | 1.28 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Dan Marcinko |
| Contact Email | dmarcinko@northbendwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/05/2026 | 02/05/2026 |
| Bid Auth. Approval | 04/09/2026 | 04/10/2026 |
| Construction Approval | 05/13/2026 | |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 85,382 | 106,727 |
| Right of Way | 0 | 0 |
| Total Design | 85,382 | 106,727 |
| Construction Engineering | 85,382 | 106,727 |
| Construction Contract | 573,488 | 716,860 |
| Other Construction | 0 | 0 |
| Total Construction | 658,870 | 823,587 |
| Total TIB Funding | 744,252 | 930,314 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| NORTH BEND | 186,062 | 20.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 186,062 | 20.0% |
Project Description
2-inch grind and overlay of the following segments SE 140th Street - 455th Ave SE to 463rd Ave SE 436th Avenue - North Bend Way to SE 136th St 468th Avenue - SE Middle Fork Rd to SE 146th St
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||