Projects — TIB Project Information
TIB Project Information
City of Brier's Vine Road Overlay
3-P-144(006)-1
3-P-144(006)-1
Vine Road Overlay
Poplar Way to S C/L
FY 2027 Arterial Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $935,229
County: Snohomish | Legislative District: 1 | Project Length: 0.75 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
| Lead Agency | BRIER |
| Funding Year | 2027 |
| Program | APP |
| Current Phase | Bid Authorization |
| Legislative District | 1 |
| Congressional District | 1 |
| Federal Route Number | 2598 |
| Project Length | 0.75 mi. |
| ADT | 3,350 |
| Functional Class | Minor |
| Type of Work | Resurfacing |
| Project Contact | John Forba |
| Contact Email | johnf@paceengrs.com |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2026 | 12/16/2025 |
| Bid Auth. Approval | 04/06/2026 | 04/07/2026 |
| Construction Approval | 05/01/2026 | |
| Project Closeout | 09/30/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 93,546 | 110,027 |
| Right of Way | 0 | 0 |
| Total Design | 93,546 | 110,027 |
| Construction Engineering | 93,546 | 110,027 |
| Construction Contract | 748,137 | 879,946 |
| Other Construction | 0 | 0 |
| Total Construction | 841,683 | 989,973 |
| Total TIB Funding | 935,229 | 1,100,000 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| BRIER | 164,771 | 15.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 164,771 | 15.0% |
Project Description
2-inch grind and overlay on Vine Road - Poplar Way to S C/L
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||