Projects — TIB Project Information
TIB Project Information
City of Snohomish's Avenue D Overlay
3-P-142(010)-1
3-P-142(010)-1
Avenue D Overlay
Multiple Locations
FY 2025 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $455,353
County: Snohomish | Legislative District: 44 | Project Length: 0.71 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
| Lead Agency | SNOHOMISH |
| Funding Year | 2025 |
| Program | APP |
| Current Phase | Design |
| Legislative District | 44 |
| Congressional District | 1 |
| Federal Route Number | 2628 |
| Project Length | 0.71 mi. |
| ADT | 0 |
| Functional Class | Minor |
| Type of Work | Resurfacing |
| Project Contact | Monty Dhaliwa |
| Contact Email | dhaliwal@snohomishwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 03/04/2024 | 12/13/2023 |
| Bid Auth. Approval | 10/01/2026 | |
| Construction Approval | 10/21/2026 | |
| Project Closeout | 10/31/2027 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 4,250 | 5,000 |
| Right of Way | 0 | 0 |
| Total Design | 4,250 | 5,000 |
| Construction Engineering | 4,250 | 5,000 |
| Construction Contract | 446,853 | 525,710 |
| Other Construction | 0 | 0 |
| Total Construction | 451,103 | 530,710 |
| Total TIB Funding | 455,353 | 535,710 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| SNOHOMISH | 80,357 | 15.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 80,357 | 15.0% |
Project Description
Grind and 2-inch overlay of Avenue D - 2nd St to 175 ft s/o 10th St
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||