Pavement condition rating is 54 and there are 12 sidewalk ramps in this segment and all are not ADA compliant. The pedestrian push buttons are not within reach range of the landings curb ramps.
Projects — TIB Project Information
TIB Project Information
City of Dupont's 2025 Center Drive Overlay Phase 4B
3-P-137(004)-1
3-P-137(004)-1
2025 Center Drive Overlay Phase 4B
Palisade Blvd to Kincaid St
FY 2027 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $543,437
County: Pierce | Legislative District: 28 | Project Length: 0.36 | TIB Engineer: Greg Armstrong | Last Payment Date: 03/25/2026
Project Information
| Lead Agency | DUPONT |
| Funding Year | 2027 |
| Program | APP |
| Current Phase | Construction |
| Legislative District | 28 |
| Congressional District | 10 |
| Federal Route Number | 2859 |
| Project Length | 0.36 mi. |
| ADT | 6,786 |
| Functional Class | Principal |
| Type of Work | Resurfacing |
| Project Contact | Gus Lim |
| Contact Email | CityEngineer@DuPontWA.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 03/25/2026 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/07/2026 | 12/18/2025 |
| Bid Auth. Approval | 03/06/2026 | 03/02/2026 |
| Construction Approval | 04/06/2026 | 04/02/2026 |
| Project Closeout | 10/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 66,400 | 83,000 |
| Right of Way | 0 | 0 |
| Total Design | 66,400 | 83,000 |
| Construction Engineering | 66,400 | 95,284 |
| Construction Contract | 728,732 | 556,536 |
| Other Construction | 0 | 0 |
| Total Construction | 795,132 | 651,820 |
| Funding Surplus | - 318,095 | |
| Total TIB Funding | 543,437 | 734,820 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| DUPONT | 191,383 | 26.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 191,383 | 26.0% |
Project Description
2-inch grind and overlay with upgrade of 12 ADA ramps and pedestrian push buttons of Center Drive between Palisade Blvd and Kincaid Street
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||