The pavement condition rating of Claremont Street - Alameda Avenue to 67th Ave W is 54.
Projects — TIB Project Information
TIB Project Information
City of Fircrest's 2024 Overlay
3-P-130(005)-1
3-P-130(005)-1
2024 Overlay
Multiple Locations
FY 2025 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $563,250
County: Pierce | Legislative District: 28 | Project Length: 0.49 | TIB Engineer: Greg Armstrong | Last Payment Date: 08/15/2025
Project Information
| Lead Agency | FIRCREST |
| Funding Year | 2025 |
| Program | APP |
| Current Phase | Audit |
| Legislative District | 28 |
| Congressional District | 10 |
| Federal Route Number | 3220 |
| Project Length | 0.49 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Tyler Bemis |
| Contact Email | tbemis@cityoffircrest.net |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 08/15/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 03/13/2024 | 03/19/2024 |
| Bid Auth. Approval | 03/07/2025 | 03/03/2025 |
| Construction Approval | 04/01/2025 | 04/02/2025 |
| Project Closeout | 10/31/2025 | 08/14/2025 |
| Audit Date | 08/15/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 97,434 | 115,266 |
| Right of Way | 0 | 0 |
| Total Design | 97,434 | 115,266 |
| Construction Engineering | 62,140 | 56,252 |
| Construction Contract | 517,835 | 509,728 |
| Other Construction | 0 | 0 |
| Total Construction | 579,975 | 565,980 |
| Funding Surplus | - 114,159 | |
| Total TIB Funding | 563,250 | 681,246 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| FIRCREST | 117,996 | 17.3% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 117,996 | 17.3% |
Project Description
Grind and 2-inch overlay of Claremont Street - Alameda Ave and 67th Ave W with 8 ADA ramps.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||