City of Normandy Park's Marine View Drive OverlayTh

3-P-112(009)-1

3-P-112(009)-1
Marine View Drive OverlayTh

SW 197th St to Edgecliff Dr SW

FY 2026 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $263,329

County: King   |   Legislative District: 33   |   Project Length: 0.31   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 12/16/2025

Project Information

Lead Agency NORMANDY PARK
Funding Year 2026
Program APP
Current Phase Construction
Legislative District 33
Congressional District 7
Federal Route Number 1109
Project Length 0.31 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Ken Courter
Contact Email kcourter@normandyparkwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 12/16/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2025 12/11/2024
Bid Auth. Approval 06/15/2025 02/03/2025
Construction Approval 05/06/2025 05/13/2025
Project Closeout 05/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 28,896 18,400
Right of Way 0 0
Total Design 28,896 18,400
     
Construction Engineering 43,089 50,844
Construction Contract 286,714 231,108
Other Construction 0 18,500
Total Construction 329,803 300,452
     
Funding Surplus - 95,370  
Total TIB Funding 263,329 318,852

Local Funding Partners

Funding Amount Percent
NORMANDY PARK 55,523 17.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 55,523 17.4%

Project Description

Marine View Drive - SW 197th St to Edgecliff Dr SW 2-inch grind, overlay, pavement repair and 4 ADA ramps

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments