The pavement condition rating of this segment is 54.
Projects — TIB Project Information
TIB Project Information
City of Normandy Park's Marine View Drive OverlayTh
3-P-112(009)-1
3-P-112(009)-1
Marine View Drive OverlayTh
SW 197th St to Edgecliff Dr SW
FY 2026 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $263,329
County: King | Legislative District: 33 | Project Length: 0.31 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/16/2025
Project Information
| Lead Agency | NORMANDY PARK |
| Funding Year | 2026 |
| Program | APP |
| Current Phase | Construction |
| Legislative District | 33 |
| Congressional District | 7 |
| Federal Route Number | 1109 |
| Project Length | 0.31 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Ken Courter |
| Contact Email | kcourter@normandyparkwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 12/16/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2025 | 12/11/2024 |
| Bid Auth. Approval | 06/15/2025 | 02/03/2025 |
| Construction Approval | 05/06/2025 | 05/13/2025 |
| Project Closeout | 05/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 28,896 | 18,400 |
| Right of Way | 0 | 0 |
| Total Design | 28,896 | 18,400 |
| Construction Engineering | 43,089 | 50,844 |
| Construction Contract | 286,714 | 231,108 |
| Other Construction | 0 | 18,500 |
| Total Construction | 329,803 | 300,452 |
| Funding Surplus | - 95,370 | |
| Total TIB Funding | 263,329 | 318,852 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| NORMANDY PARK | 55,523 | 17.4% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 55,523 | 17.4% |
Project Description
Marine View Drive - SW 197th St to Edgecliff Dr SW 2-inch grind, overlay, pavement repair and 4 ADA ramps
Existing Condition
Project Benefits
- The pavement condition rating of this segment is 54.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||