Bishop Blvd is a key arterial in the SE portion of Pullman located within a busy commercial zone. The typical street width is 44 feet (from face of curb) with two main travel lanes and a two-way left-turn lane (TWLTL). Periodic additional turn lanes and bus pull-outs are present along the route. Existing pavement distress includes longitudinal cracking (primary), wheel rutting (some), transverse cracking (minor), and alligator cracking (occasional and predominantly within the wheel path).
Projects — TIB Project Information
TIB Project Information
City of Pullman's Bishop Blvd Resurfacing
3-E-167(006)-1
3-E-167(006)-1
Bishop Blvd Resurfacing
Grand St to Fairmount St
FY 2027 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $504,930
County: Whitman | Legislative District: 9 | Project Length: 0.56 | TIB Engineer: Jonathan Heusman | Last Payment Date: 09/15/2026
Project Information
| Lead Agency | PULLMAN |
| Funding Year | 2027 |
| Program | APP |
| Current Phase | Audit |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | 7422 |
| Project Length | 0.56 mi. |
| ADT | 12,000 |
| Functional Class | Minor |
| Type of Work | Resurfacing |
| Project Contact | Cara Haley |
| Contact Email | cara.haley@pullman-wa.gov |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 09/15/2026 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 01/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2026 | 12/02/2025 |
| Bid Auth. Approval | 02/19/2026 | 02/04/2026 |
| Construction Approval | 04/08/2026 | 02/27/2026 |
| Project Closeout | 10/30/2026 | 09/01/2026 |
| Audit Date | 09/15/2026 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 16,548 | 48,094 |
| Construction Contract | 547,439 | 571,381 |
| Other Construction | 0 | 0 |
| Total Construction | 563,987 | 619,475 |
| Funding Increase | 7,588 | |
| Funding Surplus | - 66,645 | |
| Total TIB Funding | 504,930 | 619,475 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| PULLMAN | 114,545 | 18.5% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 114,545 | 18.5% |
Project Description
Grind/haul 2 in. HMA in main travel lanes, not TWLTL. 30 ft typ mill width, wider at select intersections and dedicated turn lanes (53 ft max). Surface prep, spot repair, overlay w/ 2 in. HMA, striping, upgrade ADA ramps, and other incidental work.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||