Average PCR of Selected Streets 62. Crack Seal completed on most segments.
Projects — TIB Project Information
TIB Project Information
City of Moses Lake's 2025 Chip Seal
3-E-162(001)-1
3-E-162(001)-1
2025 Chip Seal
Multiple Locations
FY 2026 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $914,998
County: Grant | Legislative District: 13 | Project Length: 6.57 | TIB Engineer: Andrew Beagle | Last Payment Date: 03/31/2026
Project Information
| Lead Agency | MOSES LAKE |
| Funding Year | 2026 |
| Program | APP |
| Current Phase | Audit |
| Legislative District | 13 |
| Congressional District | 4 |
| Federal Route Number | 6060 |
| Project Length | 6.57 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Levi Bisnett |
| Contact Email | lbisnett@cityofml.com |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 03/31/2026 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2025 | 02/11/2025 |
| Bid Auth. Approval | 05/27/2025 | 05/30/2025 |
| Construction Approval | 06/15/2025 | 06/20/2025 |
| Project Closeout | 01/15/2026 | 03/31/2026 |
| Audit Date | 03/31/2026 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 60,000 | 83,899 |
| Right of Way | 0 | 0 |
| Total Design | 60,000 | 83,899 |
| Construction Engineering | 60,000 | 98,985 |
| Construction Contract | 794,998 | 1,417,385 |
| Other Construction | 0 | 0 |
| Total Construction | 854,998 | 1,516,370 |
| Total TIB Funding | 914,998 | 1,600,269 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MOSES LAKE | 685,271 | 42.8% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 685,271 | 42.8% |
Project Description
Seal Coat and Striping Reconfiguration with 4 lanes to 3 Lanes, Intersection Optimization, Increased Parking, Bike Lanes and Sharrows, Reduced Crosswalk Lengths and future maintenance cost reductions.
Existing Condition
Project Benefits
- Asset Management
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||