Roadway surface is worn, cracked and past its design life and in need of replacement. PCR 45
Projects — TIB Project Information
TIB Project Information
City of Tenino's 2026 Overlay
2-W-977(004)-1
2-W-977(004)-1
2026 Overlay
West City Limits to Miles Sand and Gravel
FY 2027 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $462,531
County: Thurston | Legislative District: 2 | Project Length: 0.85 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | TENINO |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Construction |
| Legislative District | 2 |
| Congressional District | 3 |
| Federal Route Number | 34A2 |
| Project Length | 0.85 mi. |
| ADT | 0 |
| Functional Class | Minor |
| Type of Work | Resurfacing |
| Project Contact | Nancy Reddick |
| Contact Email | nreddick@cityoftenino.org |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/13/2026 | 01/08/2026 |
| Bid Auth. Approval | 04/30/2026 | 03/13/2026 |
| Construction Approval | 05/26/2026 | 04/17/2026 |
| Project Closeout | 08/14/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 77,325 | 81,395 |
| Right of Way | 0 | 0 |
| Total Design | 77,325 | 81,395 |
| Construction Engineering | 77,325 | 30,960 |
| Construction Contract | 515,508 | 374,520 |
| Other Construction | 0 | 0 |
| Total Construction | 592,833 | 405,480 |
| Funding Surplus | - 207,627 | |
| Total TIB Funding | 462,531 | 486,875 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| TENINO | 24,344 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 24,344 | 5.0% |
Project Description
2 inch grind and overlay
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||