TIB Project Information

City of Montesano's 2026 Chip Seal

2-W-957(020)-1

2-W-957(020)-1
2026 Chip Seal

Multiple Locations

FY 2027 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $288,468

County: Grays Harbor   |   Legislative District: 24   |   Project Length: 2.85   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency MONTESANO
Funding Year 2027
Program SCPP
Current Phase Construction
Legislative District 24
Congressional District 6
Federal Route Number 9999
Project Length 2.85 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact MIke Olden PE
Contact Email molden@montesano.us
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2026 01/27/2026
Bid Auth. Approval 04/28/2026 04/09/2026
Construction Approval 05/13/2026 04/24/2026
Project Closeout 10/30/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 333,000 321,040
Other Construction 0 0
Total Construction 333,000 321,040
     
Funding Surplus - 44,532  
Total TIB Funding 288,468 321,040

Local Funding Partners

Funding Amount Percent
MONTESANO 32,572 10.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 32,572 10.1%

Project Description

Chip seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments