A 250-foot section of pavement on E. Pioneer in the vicinity of Church street is showing signs of deterioration. This section of road is relatively flat and currently does not drain well. If not resurfaced, water will continue to reach the subgrade and accelerate the deterioration that will likely require a more costly repair.Two other areas, Fleet Street from Spruce to Broadway and S. 1st Street from Wynooche Avenue to the South end need to be pre-leveled in order to make future chip seal pos
Projects — TIB Project Information
TIB Project Information
City of Montesano's 2026 Maintenance
2-W-957(019)-1
2-W-957(019)-1
2026 Maintenance
Multiple Locations
FY 2027 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $114,610
County: Grays Harbor | Legislative District: 24 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | MONTESANO |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Construction |
| Legislative District | 24 |
| Congressional District | 6 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | |
| Project Contact | MIke Olden |
| Contact Email | molden@montesano.us |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 01/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/30/2026 | 01/27/2026 |
| Bid Auth. Approval | 03/15/2026 | 03/09/2026 |
| Construction Approval | 04/13/2026 | 04/17/2026 |
| Project Closeout | 06/30/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 116,100 | 127,510 |
| Other Construction | 0 | 0 |
| Total Construction | 116,100 | 127,510 |
| Funding Surplus | - 1,490 | |
| Total TIB Funding | 114,610 | 127,510 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MONTESANO | 12,900 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 12,900 | 10.0% |
Project Description
Grind and overlay the section of deteriorated E. Pioneer. Design this overlay to increase the cross slope in this road section to help move the water off the road and into the drainage system.Pre-level Fleet Street from Spruce to Broadway and S. 1st Street from Wynooche Avenue to the South end. Prepare for the pre-level with strategic grinding and work by City crews to upgrade shoulder/sidewalk conditions.
Existing Condition
Project Benefits
- Overlay and prelevel
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||
