The existing asphalt surface of Taylor Road is starting to show signs of distress, with several areas where the subgrade needs to be repaired
Projects — TIB Project Information
TIB Project Information
City of Kalama's Taylor Road
2-W-953(007)-1
2-W-953(007)-1
Taylor Road
Geranium St to end of road
FY 2027 Small City Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $195,816
County: Cowlitz | Legislative District: 20 | Project Length: 1.07 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | KALAMA |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Bid Authorization |
| Legislative District | 20 |
| Congressional District | 3 |
| Federal Route Number | 9999 |
| Project Length | 1.07 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Kelly Rasmussen |
| Contact Email | krasmussen@cityofkalama.com |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2026 | 12/09/2025 |
| Bid Auth. Approval | 04/30/2026 | 04/24/2026 |
| Construction Approval | 05/21/2026 | |
| Project Closeout | 09/30/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 21,850 | 23,000 |
| Right of Way | 0 | 0 |
| Total Design | 21,850 | 23,000 |
| Construction Engineering | 15,675 | 16,500 |
| Construction Contract | 158,291 | 166,625 |
| Other Construction | 0 | 0 |
| Total Construction | 173,966 | 183,125 |
| Total TIB Funding | 195,816 | 206,125 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| KALAMA | 10,309 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 10,309 | 5.0% |
Project Description
Chip seal
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||