City of La Center's 2026 Maintenance

2-W-949(005)-1

2-W-949(005)-1
2026 Maintenance

Multiple Locations

FY 2027 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $81,315

County: Clark   |   Legislative District: 20   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency LA CENTER
Funding Year 2027
Program SCPP
Current Phase Construction
Legislative District 20
Congressional District 3
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work
Project Contact Tracy Coleman
Contact Email tcoleman@ci.lacenter.wa.us
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 01/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/08/2026 01/29/2026
Bid Auth. Approval 05/15/2026 02/06/2026
Construction Approval 06/08/2026 04/20/2026
Project Closeout 09/04/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 81,315 126,623
Other Construction 0 0
Total Construction 81,315 126,623
     
Total TIB Funding 81,315 126,623

Local Funding Partners

Funding Amount Percent
LA CENTER 45,308 35.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 45,308 35.8%

Project Description

Crack seal application and full depth repair of potholes.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments