Projects — TIB Project Information
TIB Project Information
City of Forks's 2025 Red Town Initiative
2-W-825(004)-1
2-W-825(004)-1
2025 Red Town Initiative
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $1,756,338
County: Clallam | Legislative District: 24 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/01/2025
Project Information
| Lead Agency | FORKS |
| Funding Year | 2026 |
| Program | SCPP |
| Current Phase | Construction |
| Legislative District | 24 |
| Congressional District | 6 |
| Federal Route Number | 9999 |
| Project Length | 0.10 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Devin Jackson |
| Contact Email | devin@jacksoncivil.com |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 11/01/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 09/27/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 11/01/2024 | 10/16/2024 |
| Bid Auth. Approval | 05/01/2025 | 04/24/2025 |
| Construction Approval | 06/15/2025 | 06/16/2025 |
| Project Closeout | 10/31/2025 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 180,328 | 100,000 |
| Right of Way | 0 | 0 |
| Total Design | 180,328 | 100,000 |
| Construction Engineering | 180,328 | 150,000 |
| Construction Contract | 1,639,344 | 1,598,777 |
| Other Construction | 0 | 0 |
| Total Construction | 1,819,672 | 1,748,777 |
| Funding Surplus | - 243,662 | |
| Total TIB Funding | 1,756,338 | 1,848,777 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| FORKS | 92,439 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 92,439 | 5.0% |
Project Description
Otta or chip seal
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||