All roads in Wilkeson were evaluated in June 2024 to determine PCR scores. The selected streets feature PCR scores ranging between 81 and 50. The street with the lowest score, Cothary Street, is visibly worn and exhibits fatigue that is expected to worsen if not addressed. Indications of wear can be seen on the remaining streets to varying extents. Chip seal has been selected as a cost-effective measure that will maintain the condition of each pavement and prevent severe deterioration.
Projects — TIB Project Information
TIB Project Information
Town of Wilkeson's 2026 Townwide Chip Seal
2-P-816(004)-1
2-P-816(004)-1
2026 Townwide Chip Seal
Multiple Locations
FY 2027 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $234,466
County: Pierce | Legislative District: 31 | Project Length: 0.72 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
| Lead Agency | WILKESON |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Design |
| Legislative District | 31 |
| Congressional District | 8 |
| Federal Route Number | 9999 |
| Project Length | 0.72 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Marie Wellock |
| Contact Email | clerk@townofwilkeson.com |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/15/2026 | 12/16/2025 |
| Bid Auth. Approval | 05/05/2026 | |
| Construction Approval | 06/01/2026 | |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 27,053 | 27,053 |
| Right of Way | 0 | 0 |
| Total Design | 27,053 | 27,053 |
| Construction Engineering | 27,053 | 27,053 |
| Construction Contract | 180,360 | 180,360 |
| Other Construction | 0 | 0 |
| Total Construction | 207,413 | 207,413 |
| Total TIB Funding | 234,466 | 234,466 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| WILKESON | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Chip Seal of the following segment Cothary Street - Hill St to Short St Short Street - Brierhill Blvd to Cothary St Hill Street - Church St to Long St Railroad Avenue - Church St to E C/L Hill Street - Long Street to Cothary St Cedar Street - Church St to Railroad Ave
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||