Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Carnation's Royal Glen Scrub Seal

2-P-801(007)-1

2-P-801(007)-1
Royal Glen Scrub Seal

Multiple Locations

FY 2027 Small City Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $168,909

County: King   |   Legislative District: 12   |   Project Length: 0.31   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency CARNATION
Funding Year 2027
Program SCPP
Current Phase Bid Authorization
Legislative District 12
Congressional District 8
Federal Route Number 9999
Project Length 0.31 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Lora Wilmes
Contact Email lora.wilmes@carnationwa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/15/2026 12/22/2025
Bid Auth. Approval 04/15/2026 03/19/2026
Construction Approval 05/04/2026
Project Closeout 11/30/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 18,345 20,383
Right of Way 0 0
Total Design 18,345 20,383
     
Construction Engineering 18,345 20,383
Construction Contract 132,219 146,910
Other Construction 0 0
Total Construction 150,564 167,293
     
Total TIB Funding 168,909 187,676

Local Funding Partners

Funding Amount Percent
CARNATION 18,767 10.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 18,767 10.0%

Project Description

Scrub Seal the following segments Kings Court - Blanche St to N EOR Royal Court - Regal St to N EOR Regency Place - Regal Place to S EOR Queen Court - Regal St to W EOR Palace Court - Regal St to W EOR Regal Avenue NE - Regal St to SE EOR

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments