The Town of Woodway completed a street inventory analysis in June 2024 and identified four roadway segments in need of overlay and repair. These segments have Pavement Condition Ratings (PCR) ranging from 54 to 59, indicating poor pavement quality and collectively represent some of the Towns most critical pavement repair needs.
Projects — TIB Project Information
TIB Project Information
Town of Woodway's 2026 Overlay
2-P-147(001)-1
2-P-147(001)-1
2026 Overlay
Multiple Locations
FY 2027 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $581,521
County: Snohomish | Legislative District: 32 | Project Length: 0.56 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
| Lead Agency | WOODWAY |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Construction |
| Legislative District | 32 |
| Congressional District | 2 |
| Federal Route Number | 9999 |
| Project Length | 0.56 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | John Forba |
| Contact Email | johnf@paceengrs.com |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2026 | 12/08/2025 |
| Bid Auth. Approval | 04/15/2026 | 04/07/2026 |
| Construction Approval | 05/01/2026 | 04/30/2026 |
| Project Closeout | 10/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 58,158 | 52,787 |
| Right of Way | 0 | 0 |
| Total Design | 58,158 | 52,787 |
| Construction Engineering | 57,854 | 61,217 |
| Construction Contract | 465,509 | 601,691 |
| Other Construction | 0 | 0 |
| Total Construction | 523,363 | 662,908 |
| Total TIB Funding | 581,521 | 715,695 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| WOODWAY | 134,174 | 18.7% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 134,174 | 18.7% |
Project Description
2-inch grind and overlay of the following segments 113th Place W - 238th St SW to 240th St SW 116th Avenue W - S C/L to 241st St 238th Street SW - Woodway Prk Rd to Timber Lane Bella Coola Rd - Makah to 117th Pl W
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||