The pavement condition is currently cracked both transversely and longitudinally. The location has several areas where insufficient drainage has led to intrusion under the pavement, allowing for potholes to develop.
Projects — TIB Project Information
TIB Project Information
City of Zillah's 2026 Overlay
2-E-947(005)-1
2-E-947(005)-1
2026 Overlay
W 1st Ave to end of road
FY 2027 Small City Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $290,745
County: Yakima | Legislative District: 15 | Project Length: 0.16 | TIB Engineer: Jonathan Heusman | Last Payment Date: 04/16/2026
Project Information
| Lead Agency | ZILLAH |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Bid Authorization |
| Legislative District | 15 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.16 mi. |
| ADT | 1,801 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Ardele Steele |
| Contact Email | asteele@cityofzillah.us |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 04/16/2026 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/05/2026 | 12/16/2025 |
| Bid Auth. Approval | 04/03/2026 | 04/21/2026 |
| Construction Approval | 06/15/2026 | |
| Project Closeout | 09/21/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 31,311 | 34,790 |
| Right of Way | 0 | 0 |
| Total Design | 31,311 | 34,790 |
| Construction Engineering | 35,784 | 39,760 |
| Construction Contract | 223,650 | 248,500 |
| Other Construction | 0 | 0 |
| Total Construction | 259,434 | 288,260 |
| Total TIB Funding | 290,745 | 323,050 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ZILLAH | 32,305 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 32,305 | 10.0% |
Project Description
2 inch grind and overlay with an overlay going from 0.17 ' to 0.33' at the center to restore the crown and eliminate existing drainage issues.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||