Postma Road from N. Rivard Road to the canal/City Limits has an existing asphalt pavement depth of 3 inches. This section of Postma is the remaining section that has yet to be resurfaced within the City Limits. The approximate width varies from 23 feet to 33 feet. There are no non-compliant ADA ramps.
Projects — TIB Project Information
TIB Project Information
City of Moxee's 2026 Overlay
2-E-943(009)-1
2-E-943(009)-1
2026 Overlay
N Rivard Rd to East City Limits
FY 2027 Small City Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $210,573
County: Yakima | Legislative District: 15 | Project Length: 0.26 | TIB Engineer: Jonathan Heusman | Last Payment Date: 04/17/2026
Project Information
| Lead Agency | MOXEE |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Bid Authorization |
| Legislative District | 15 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.26 mi. |
| ADT | 1,350 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Byron Adams |
| Contact Email | jeff.burkett@co.yakima.wa.us |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 04/17/2026 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/20/2026 | 03/27/2026 |
| Bid Auth. Approval | 05/06/2026 | 04/30/2026 |
| Construction Approval | 05/26/2026 | |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 19,143 | 21,270 |
| Right of Way | 0 | 0 |
| Total Design | 19,143 | 21,270 |
| Construction Engineering | 22,095 | 24,550 |
| Construction Contract | 169,335 | 188,150 |
| Other Construction | 0 | 0 |
| Total Construction | 191,430 | 212,700 |
| Total TIB Funding | 210,573 | 233,970 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MOXEE | 23,397 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 23,397 | 10.0% |
Project Description
2' grind and overlay from curb to curb or edge of lanes.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||