The City of Moxee has incurred severe roadway cracking throughout the city limits.
Projects — TIB Project Information
TIB Project Information
City of Moxee's 2025 Crack Seal
2-E-943(008)-1
2-E-943(008)-1
2025 Crack Seal
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Closeout
Total TIB Funding : $148,751
County: Yakima | Legislative District: 13 | Project Length: 0.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 04/30/2026
Project Information
| Lead Agency | MOXEE |
| Funding Year | 2026 |
| Program | SCPP |
| Current Phase | Closeout |
| Legislative District | 13, 15 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | |
| Project Contact | Byron Adams |
| Contact Email | byron.adams@co.yakima.wa.us |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 04/30/2026 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2025 | 12/17/2024 |
| Bid Auth. Approval | 06/01/2025 | 03/18/2025 |
| Construction Approval | 07/15/2025 | 04/10/2025 |
| Project Closeout | 03/31/2026 | 04/23/2026 |
| Audit Date | 04/30/2026 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 165,567 | 165,279 |
| Other Construction | 0 | 0 |
| Total Construction | 165,567 | 165,279 |
| Funding Surplus | - 16,816 | |
| Total TIB Funding | 148,751 | 165,279 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MOXEE | 16,528 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 16,528 | 10.0% |
Project Description
Clean-and-seal existing lateral and horizontal cracks.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||