Projects — TIB Project Information
TIB Project Information
City of Roslyn's 2025 Seal Coat
2-E-932(006)-1
2-E-932(006)-1
2025 Seal Coat
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Closeout
Total TIB Funding : $452,812
County: Kittitas | Legislative District: 13 | Project Length: 2.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 04/30/2026
Project Information
| Lead Agency | ROSLYN |
| Funding Year | 2026 |
| Program | SCPP |
| Current Phase | Closeout |
| Legislative District | 13 |
| Congressional District | 8 |
| Federal Route Number | 9999 |
| Project Length | 2.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Bryson Simplot |
| Contact Email | publicworks@ci.roslyn.wa.us |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 04/30/2026 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 01/24/2025 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/28/2025 | 02/24/2025 |
| Bid Auth. Approval | 05/31/2025 | 05/29/2025 |
| Construction Approval | 06/19/2025 | 06/26/2025 |
| Project Closeout | 04/15/2026 | 04/23/2026 |
| Audit Date | 04/30/2026 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 53,000 | 55,789 |
| Right of Way | 0 | 0 |
| Total Design | 53,000 | 55,789 |
| Construction Engineering | 53,000 | 36,020 |
| Construction Contract | 594,000 | 384,835 |
| Other Construction | 0 | 0 |
| Total Construction | 647,000 | 420,855 |
| Funding Surplus | - 247,188 | |
| Total TIB Funding | 452,812 | 476,644 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ROSLYN | 23,832 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 23,832 | 5.0% |
Project Description
Seal coat treatment and pulverize followed by double seal coat as needed.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||