Town of Marcus's 2025 Fog Seal

2-E-904(003)-1

2-E-904(003)-1
2025 Fog Seal

Multiple Locations

FY 2026 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $24,221

County: Stevens   |   Legislative District: 7   |   Project Length: 2.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 08/06/2025

Project Information

Lead Agency MARCUS
Funding Year 2026
Program SCPP
Current Phase Construction
Legislative District 7
Congressional District 5
Federal Route Number 9999
Project Length 2.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Angie Sphuler
Contact Email town.marcusclerk@gmail.com
TIB Engineer Andrew Beagle
Last Payment Date 08/06/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 12/15/2024 12/03/2024
Bid Auth. Approval 04/30/2025 06/02/2025
Construction Approval 05/30/2025 06/02/2025
Project Closeout 09/30/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 25,290 0
Right of Way 0 0
Total Design 25,290 0
     
Construction Engineering 25,290 0
Construction Contract 180,640 24,221
Other Construction 0 0
Total Construction 205,930 24,221
     
Funding Surplus - 206,999  
Total TIB Funding 24,221 24,221

Local Funding Partners

Funding Amount Percent
MARCUS 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Potential chip seal on one segment, mostly fog seal and some pavement repair townwide.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments