Pavement distresses throughout the local network including longitudinal, transverse and alligator cracking.
Projects — TIB Project Information
TIB Project Information
City of Medical Lake's 2025 Street Maintenance
2-E-897(009)-1
2-E-897(009)-1
2025 Street Maintenance
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $160,337
County: Spokane | Legislative District: 6 | Project Length: 0.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/09/2026
Project Information
| Lead Agency | MEDICAL LAKE |
| Funding Year | 2026 |
| Program | SCPP |
| Current Phase | Construction |
| Legislative District | 6 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Scott Duncan |
| Contact Email | sduncan@medical-lake.org |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 01/09/2026 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2025 | 01/02/2025 |
| Bid Auth. Approval | 02/01/2025 | 05/05/2025 |
| Construction Approval | 02/15/2025 | 05/05/2025 |
| Project Closeout | 10/30/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 160,337 | 168,776 |
| Other Construction | 0 | 0 |
| Total Construction | 160,337 | 168,776 |
| Total TIB Funding | 160,337 | 168,776 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MEDICAL LAKE | 8,439 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 8,439 | 5.0% |
Project Description
Crack seal and pavement repair on select streets.
Existing Condition
Project Benefits
- Maintain pavement assets in a state of good repair.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||