The current average pavement rating score for Davenport is 68.4, and the goal is to increase this score.
Projects — TIB Project Information
TIB Project Information
City of Davenport's 2026 Scrub Seal
2-E-870(006)-1
2-E-870(006)-1
2026 Scrub Seal
Multiple Locations
FY 2027 Small City Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $1,193,545
County: Lincoln | Legislative District: 9 | Project Length: 6.38 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
| Lead Agency | DAVENPORT |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Bid Authorization |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 6.38 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Steven Goemmel |
| Contact Email | sgoemmel@davenportwa.us |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2026 | 12/04/2025 |
| Bid Auth. Approval | 06/01/2026 | 04/29/2026 |
| Construction Approval | 05/30/2026 | |
| Project Closeout | 09/30/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 85,255 | 89,759 |
| Right of Way | 0 | 0 |
| Total Design | 85,255 | 89,759 |
| Construction Engineering | 85,255 | 89,759 |
| Construction Contract | 1,023,035 | 1,077,084 |
| Other Construction | 0 | 0 |
| Total Construction | 1,108,290 | 1,166,843 |
| Total TIB Funding | 1,193,545 | 1,256,602 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| DAVENPORT | 63,057 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 63,057 | 5.0% |
Project Description
Chip or Scrub Seal select streets on local network.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||