The Towns average PCR rating is 66.1. Heavily trafficked areas shown obvious degradation. Crack seal was applied to most of the road network in Summer 2025, except in portions with excessive cracking and where recent improvements were made to the roads surrounding Almira Elementary made such preservation techniques unnecessary.
Projects — TIB Project Information
TIB Project Information
Town of Almira's 2026 Chip and Scrub Seal
2-E-868(009)-1
2-E-868(009)-1
2026 Chip and Scrub Seal
Multiple Locations
FY 2027 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $616,820
County: Lincoln | Legislative District: 9 | Project Length: 14.04 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
| Lead Agency | ALMIRA |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Design |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 14.04 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Tim Jennings |
| Contact Email | almiratownhall@gmail.com |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 12/01/2025 | 12/01/2025 |
| Bid Auth. Approval | 03/30/2026 | |
| Construction Approval | 04/29/2026 | |
| Project Closeout | 07/10/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 51,403 | 51,403 |
| Right of Way | 0 | 0 |
| Total Design | 51,403 | 51,403 |
| Construction Engineering | 51,403 | 51,403 |
| Construction Contract | 514,014 | 514,014 |
| Other Construction | 0 | 0 |
| Total Construction | 565,417 | 565,417 |
| Total TIB Funding | 616,820 | 616,820 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ALMIRA | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Scrub or chip seal on select streets.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||