The roads require a preventative maintenance measure that can address the cracking damage present on the existing roadways.
Projects — TIB Project Information
TIB Project Information
City of Royal City's 2026 Crack Seal
2-E-864(008)-1
2-E-864(008)-1
2026 Crack Seal
Multiple Locations
FY 2027 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $98,000
County: Grant | Legislative District: 13 | Project Length: 0.00 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
| Lead Agency | ROYAL CITY |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Design |
| Legislative District | 13 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | |
| Project Contact | Janice Flynn |
| Contact Email | janice@royalcitywa.org |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 01/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2026 | 12/08/2025 |
| Bid Auth. Approval | 04/01/2026 | |
| Construction Approval | 06/01/2026 | |
| Project Closeout | 10/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 98,000 | 98,000 |
| Other Construction | 0 | 0 |
| Total Construction | 98,000 | 98,000 |
| Total TIB Funding | 98,000 | 98,000 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ROYAL CITY | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
City-wide crack seal.
Existing Condition
Project Benefits
- Crack seal to preserve the roadways from further deterioration. Also preps the roadways for a future chip seal project.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||