Projects — TIB Project Information
TIB Project Information
City of Grand Coulee's 2022 Seal Coat Award
2-E-859(006)-1
2-E-859(006)-1
2022 Seal Coat Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $243,714
County: Grant | Legislative District: 12 | Project Length: 0.43 | TIB Engineer: Jesse Larson | Last Payment Date: 12/02/2024
Project Information
| Lead Agency | GRAND COULEE |
| Funding Year | 2024 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 12 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.43 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Dennis Francis |
| Contact Email | shopboss@gccitywa.org |
| TIB Engineer | Jesse Larson |
| Last Payment Date | 12/02/2024 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/02/2022 | |
| Delayed Project Date | 07/01/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2023 | 12/14/2022 |
| Bid Auth. Approval | 02/15/2024 | 05/24/2024 |
| Construction Approval | 06/15/2024 | 06/28/2024 |
| Project Closeout | 10/31/2024 | 11/18/2024 |
| Audit Date | 12/02/2024 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 9,040 | 19,002 |
| Right of Way | 0 | 0 |
| Total Design | 9,040 | 19,002 |
| Construction Engineering | 9,040 | 16,700 |
| Construction Contract | 60,900 | 207,734 |
| Other Construction | 0 | 278 |
| Total Construction | 69,940 | 224,712 |
| Funding Increase | 196,707 | |
| Funding Surplus | - 31,973 | |
| Total TIB Funding | 243,714 | 243,714 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| GRAND COULEE | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Chip Seal of the following segments Main Street - Spokane Wy to Federal Ave Federal Avenue - Main St to Spokane Wy Federal Avenue - Spokane Wy to W Grand Coulee Ave (SR 174)
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||