City of George's 2025 Otta Seal

2-E-858(009)-1

2-E-858(009)-1
2025 Otta Seal

Multiple Locations

FY 2026 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $563,214

County: Grant   |   Legislative District: 13   |   Project Length: 4.02   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 04/14/2026

Project Information

Lead Agency GEORGE
Funding Year 2026
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 4
Federal Route Number 9999
Project Length 4.02 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Aaron Harwood
Contact Email pwd@cityofgeorge.org
TIB Engineer Jonathan Heusman
Last Payment Date 04/14/2026
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/01/2025 01/27/2025
Bid Auth. Approval 04/30/2025 04/29/2025
Construction Approval 05/16/2025 05/29/2025
Project Closeout 04/15/2026 04/13/2026
Audit Date   04/14/2026
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 57,660 46,972
Right of Way 0 0
Total Design 57,660 46,972
     
Construction Engineering 57,660 47,824
Construction Contract 576,490 468,418
Other Construction 0 0
Total Construction 634,150 516,242
     
Funding Surplus - 128,596  
Total TIB Funding 563,214 563,214

Local Funding Partners

Funding Amount Percent
GEORGE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Single chip seal on some paved streets. Pulverize and double chip seal on other streets with worse deterioration.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.