 Projects — TIB Project Information

TIB Project Information

Town of Coulee City's 2025 Otta Seal

2-E-856(006)-1

2-E-856(006)-1
2025 Otta Seal

Multiple Locations

FY 2026 Small City Preservation Program
Current Phase : Closeout
Total TIB Funding : $539,980

County: Grant   |   Legislative District: 7   |   Project Length: 1.61   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 04/30/2026

Project Information

Lead Agency COULEE CITY
Funding Year 2026
Program SCPP
Current Phase Closeout
Legislative District 7
Congressional District 4
Federal Route Number 9999
Project Length 1.61 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Natalie Garrett
Contact Email tcoulee@odessaoffice.com
TIB Engineer Andrew Beagle
Last Payment Date 04/30/2026
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2025 12/23/2024
Bid Auth. Approval 05/01/2025 04/25/2025
Construction Approval 05/14/2025 05/25/2025
Project Closeout 01/15/2026 04/21/2026
Audit Date   04/30/2026
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 23,496 29,349
Right of Way 0 0
Total Design 23,496 29,349
     
Construction Engineering 70,487 62,805
Construction Contract 469,933 453,904
Other Construction 0 0
Total Construction 540,420 516,709
     
Funding Surplus - 23,936  
Total TIB Funding 539,980 546,058

Local Funding Partners

Funding Amount Percent
COULEE CITY 6,078 1.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 6,078 1.1%

Project Description

Otta Seal with several prep options depending on the segment.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments