Town of Mansfield's Walnut Street Overlay

2-E-852(009)-1

2-E-852(009)-1
Walnut Street Overlay

Cemetery Rd to 2nd Ave

FY 2027 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $266,000

County: Douglas   |   Legislative District: 7   |   Project Length: 0.50   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency MANSFIELD
Funding Year 2027
Program SCPP
Current Phase Design
Legislative District 7
Congressional District 4
Federal Route Number 9999
Project Length 0.50 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Tricia Sima
Contact Email mansfield@nwi.net
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2026 12/11/2025
Bid Auth. Approval 05/01/2026
Construction Approval 06/01/2026
Project Closeout 10/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 30,000 30,000
Right of Way 0 0
Total Design 30,000 30,000
     
Construction Engineering 30,000 30,000
Construction Contract 206,000 206,000
Other Construction 0 0
Total Construction 236,000 236,000
     
Total TIB Funding 266,000 266,000

Local Funding Partners

Funding Amount Percent
MANSFIELD 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Repair and overlay existing roadway.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.