These roads exhibit extensive longitudinal and transverse cracking, along with surface openings, indicating early-stage pavement distress.
Projects — TIB Project Information
TIB Project Information
Town of Lind's 2026 Maintenance
2-E-843(004)-1
2-E-843(004)-1
2026 Maintenance
Multiple Locations
FY 2027 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $97,850
County: Adams | Legislative District: 9 | Project Length: 0.00 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
| Lead Agency | LIND |
| Funding Year | 2027 |
| Program | SCPP |
| Current Phase | Design |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | |
| Project Contact | Paula Bell |
| Contact Email | mayorbell.lind@gmail.com |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 01/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2026 | 12/02/2025 |
| Bid Auth. Approval | 05/01/2026 | |
| Construction Approval | 06/01/2026 | |
| Project Closeout | 09/01/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 97,850 | 97,850 |
| Other Construction | 0 | 0 |
| Total Construction | 97,850 | 97,850 |
| Total TIB Funding | 97,850 | 97,850 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| LIND | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Perform a citywide crack seal.
Existing Condition
Project Benefits
- Prevent further deterioration of the road and to prepare for a chip seal in a following year.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||