TIB Project Information
City of Ferndale's Complete Streets Award
C-W-985(001)-1
C-W-985(001)-1
Complete Streets Award
March 2019 Selection
FY 2020 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $300,000
County: Whatcom | Legislative District: 42 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 05/02/2019
Project Information
Lead Agency | FERNDALE |
Funding Year | 2020 |
Program | CSP |
Current Phase | Audit |
Legislative District | 42 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Pedestrian |
Project Contact | Kevin Renz |
Contact Email | kevinrenz@cityofferndale.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 05/02/2019 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/28/2019 | |
Delayed Project Date | 07/01/2021 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 05/01/2019 | |
Bid Auth. Approval | 05/01/2019 | |
Construction Approval | 05/01/2019 | 04/30/2019 |
Project Closeout | 02/28/2021 | 02/18/2021 |
Audit Date | 02/18/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 300,000 | 300,000 |
Other Construction | 0 | 0 |
Total Construction | 300,000 | 300,000 |
Total TIB Funding | 300,000 | 300,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
FERNDALE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
First and Main Intersection | Pedestrian | Mar 2019 | $100,000 | $100,000 | |
Improve safety by installing pedestrian acitvated signal, increase signage, and modify channelization. Replace non ADA compliant ramps where necessary. | |||||
Thornton and Maureen Crosswalk | Pedestrian | Mar 2019 | $50,000 | $50,000 | |
Improve pedestrian safety by installing pedestrian activated signal at important school crossing an high ADT route. | |||||
Vista Drive ADA Improvments | Pedestrian | Mar 2019 | $100,000 | $100,000 | |
Improve crosswalk on Vista Drive. Correct ADA slopes and add ADA ramps on west side of intersection. Install pedestrian activated signal. | |||||
Lower Downtown ADA Improvements | Pedestrian | Mar 2019 | $50,000 | $50,000 | |
Install ADA compliant ramps at non compliant intersections on Alder Street |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |