TIB Project Information

City of Ferndale's Complete Streets Award

C-W-985(001)-1

C-W-985(001)-1
Complete Streets Award

March 2019 Selection

FY 2020 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $300,000

County: Whatcom   |   Legislative District: 42   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 05/02/2019

Project Information

Lead Agency FERNDALE
Funding Year 2020
Program CSP
Current Phase Audit
Legislative District 42
Congressional District 1
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Local Access
Type of Work Pedestrian
Project Contact Kevin Renz
Contact Email kevinrenz@cityofferndale.org
TIB Engineer Chris Langhoff
Last Payment Date 05/02/2019
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   03/28/2019
Delayed Project Date 07/01/2021  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2019
Bid Auth. Approval 05/01/2019
Construction Approval 05/01/2019 04/30/2019
Project Closeout 02/28/2021 02/18/2021
Audit Date   02/18/2021
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 300,000 300,000
Other Construction 0 0
Total Construction 300,000 300,000
     
Total TIB Funding 300,000 300,000

Local Funding Partners

Funding Amount Percent
FERNDALE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
First and Main Intersection Pedestrian Mar 2019 $100,000 $100,000
Improve safety by installing pedestrian acitvated signal, increase signage, and modify channelization. Replace non ADA compliant ramps where necessary.
Thornton and Maureen Crosswalk Pedestrian Mar 2019 $50,000 $50,000
Improve pedestrian safety by installing pedestrian activated signal at important school crossing an high ADT route.
Vista Drive ADA Improvments Pedestrian Mar 2019 $100,000 $100,000
Improve crosswalk on Vista Drive. Correct ADA slopes and add ADA ramps on west side of intersection. Install pedestrian activated signal.
Lower Downtown ADA Improvements Pedestrian Mar 2019 $50,000 $50,000
Install ADA compliant ramps at non compliant intersections on Alder Street

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments