Clark County's NE 88th Street
Overview
Clark County's NE 88th Street project was selected for funding in November 2007.

TIB contributed $2,912,136 in funding toward the $6,115,364 total cost of the project.

For more information about this project, contact:
Jason Phelps
Project Engineer
(360) 586-1151
JasonP@TIB.wa.gov
View Picture Gallery
More Project Information
9-W-006(025)-1
NE 88th Street
NE St. Johns Rd to NE Andresen Rd
FY 2009 Urban Corridor Program
Project Length: 1.13 mi.
ADT: 11,723
Functional Class: Collector
Type of Work: Reconstruction
Total TIB Funding: $2,912,136
Total Project Costs: $6,115,364
Funding Partners
  • $2,912,136 from TIB's Urban Corridor Program (UCP)
  • $382,747 from Clark County
  • $1,620,481 from Traffic Impact Fees
  • $1,200,000 from STP Funds
Project Benefits
  • Decreases congestion
  • Reduces accidents
  • Provides a multi-modal corridor
More Project Information
 
About the Project
This project will widen the roadway to include two through lanes and a continuous left-turn lane, with bike lanes and sidewalks on both sides.
Project Location