Points Maximum

Mobility   30
Level of Service   0 to 10
Truck Route (T-1 to T-3)   0 to 3
Traffic Signal Interconnection   1
Network Development   10
  Extends Improvements 0 to 5  
  Completes Gap 5 to 10  
  Completes Corridor 10 to 15  
  New network connection 5 to 10  
Creates or Improves Freight Facility Access   0 to 5
Peak Hour Buses (1 pt per 2 Buses)   0 to 3
Points Maximum

Local Support   30
Matching Funds   25
  Lead Agency Funding - 1 pt per 1% 0 to 5  
  Overmatch Funding - 1 pt per 2% above Minimum Local Match 0 to 10  
  Private Partner Funding - 1 pt per 1% 0 to 10  
Ready to Construct (5 max)   5
  (Must be complete at time of application)    
  Environmental Permits Approved 1  
  Design Complete 2  
  Right of Way Acquisition Complete 2  
Points Maximum

Growth and Development   15
  Provides or improves access to CBD or designated Activity Center 0 to 10  
  Increases in Permitted Employment Center Square Footage 0 to 5  
  Increases Permitted for Residential Density 0 to 5  
  Eliminates Concurrency Violation or Transportation Moratorium 0 to 5  
  Joint City/County-funded Application within Potential Annexation Area 3  
  Project is in an Annexation Area 1  
Points Maximum
Safety   10
Correctable Accident History   0 to 10
Implement State Policy Goals   0 to 5
Provide Access Management   5
  Add non-traversable median greater than 50% of project length 3  
  Add c-curb at intersections or less than 50% project length 2  
  Reduce Access Points 1  
Eliminate Existing At-Grade Crossing   0 to 5
Points Maximum

Sustainability   15
Modal Measures   15
  Completes gap in HOV system 3  
  Adds HOV Lane each direction 2  
  Adds Queue Jump or Transit Only Lane 1  
  Improves non-motorized access to Park & Ride or Transit center 1  
  Completes gap in Bicycle Route 3  
  Extends Bicycle Route 2  
  Construct 10-foot separated path or two 5-foot striped lanes 2  
  Install more that one bike parking facility along the project (multiple bike racks) 1  
  Sidewalk wider that TIB minimum (5 ft) 0 to 3  
  Planter Strip (3 foot minimum) 3  
Energy Measures   9
  Replace or Install new LED street lights throughout the project 0 to 3  
  Replace or Install new LED traffic signals throughout the project 0 to 2  
  Install Solar Power Panels or on-site power generation technology to support facilities in the road right of way 1  
  Emerging Technologies 0 to 3  
Environmental Measures   7
  Eliminate water detention through Low Impact Development (LID) / Natural Drainage Practices (NDP) (e.g. ecology embankment, permeable pavement) on-site to address 100% of all project impervious surfaces 3  
  Eliminate water detention through Low Impact Development (LID) / Natural Drainage Practices (NDP) (e.g. ecology embankment, permeable pavement) on-site to address 25% to 75% of all project impervious surfaces 0 to 3  
  Vegetated areas left undisturbed, or compost-amend soil with native plantings 1  
  Hardscaping or climate appropriate plantings 1  
  Emerging Technologies 0 to 3  
Recycling Measures   9
  On-site reuse of pavement 3  
  On-site reuse of subsurface material 1  
  On-site reuse of other materials 0 to 3  
  Use of recycled pavement (hauled in) 2  
  Use of recycled subsurface materials 1  
  use of recycled organic materials (hauled in) 1  
  Use of other recycled products 0 to 2