City of Westport's 2017 Emergency Pavement Repair Project

2-W-960(004)-1

2-W-960(004)-1
2017 Emergency Pavement Repair Project

Various Locations

FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $19,000

County: Grays Harbor   |   Legislative District: 19   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 10/02/2017

Project Information

Lead Agency WESTPORT
Funding Year 2017
Program SCPP
Current Phase Audit
Legislative District 19
Congressional District 6
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Kevin Goodrich
Contact Email pwd@ci.westport.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 10/02/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   06/01/2017
Delayed Project Date 07/01/2019  
Predesign Approval
Design Approval 06/15/2017 06/26/2017
Bid Auth. Approval 06/15/2017 06/26/2017
Construction Approval 06/15/2017 06/26/2017
Project Closeout 08/31/2017 09/29/2017
Audit Date   10/02/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 29,844 20,000
Other Construction 0 0
Total Construction 29,844 20,000
     
Funding Surplus - 10,844  
Total TIB Funding 19,000 20,000

Local Funding Partners

Funding Amount Percent
WESTPORT 1,000 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,000 5.0%

Project Description

See approved repair list

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments