Projects — TIB Project Information
TIB Project Information
City of Oakville's FY 2009 Seal Coat Project
2-W-958(001)-1
2-W-958(001)-1
FY 2009 Seal Coat Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $50,688
County: Grays Harbor | Legislative District: 19 | Project Length: 1.51 | TIB Engineer: Chris Langhoff | Last Payment Date: 09/09/2009
Project Information
Lead Agency | OAKVILLE |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 19 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 1.51 mi. |
ADT | 250 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | Daniel Thompson |
Contact Email | danwaterman@comcast.net |
TIB Engineer | Chris Langhoff |
Last Payment Date | 09/09/2009 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/31/2008 | 03/05/2008 |
Bid Auth. Approval | 03/31/2008 | 03/05/2008 |
Construction Approval | 07/22/2009 | 09/04/2009 |
Project Closeout | 09/30/2008 | 09/04/2009 |
Audit Date | 09/09/2009 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 45,190 | 50,688 |
Other Construction | 0 | 0 |
Total Construction | 45,190 | 50,688 |
Funding Increase | 5,498 | |
Total TIB Funding | 50,688 | 50,688 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OAKVILLE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Chip seal the following segments Second Street - Oak Street to Eagle Street Main Street - Oak Street to Park Street Oak Street - State Street to Blockhouse Road Murray Street - Pine Street(SR 12) to Campion Road Newton Street - Harris Street to Eagle Street Eagle Street - Newton Street to 1st Street Eagle Street - 3rd Street to 4th Street Harris Avenue - 3rd Street to Newton Street
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |