City of Montesano's FY 2020 Overlay Project
2-W-957(003)-1
2-W-957(003)-1
FY 2020 Overlay Project
Multiple Locations
FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $84,561
County: Grays Harbor | Legislative District: 19 | Project Length: 0.11 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/01/2019
Project Information
Lead Agency | MONTESANO |
Funding Year | 2020 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 19 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 0.11 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Mike Olden |
Contact Email | molden@montesano.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 10/01/2019 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 12/13/2018 |
Bid Auth. Approval | 05/01/2019 | 04/19/2019 |
Construction Approval | 06/01/2019 | 05/14/2019 |
Project Closeout | 08/31/2019 | 09/19/2019 |
Audit Date | 10/01/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 81,000 | 96,666 |
Other Construction | 0 | 0 |
Total Construction | 81,000 | 96,666 |
Funding Increase | 3,561 | |
Total TIB Funding | 84,561 | 96,666 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MONTESANO | 12,105 | 12.5% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 12,105 | 12.5% |
Project Description
Grind and Pave 570 feet of W. Broadway from the Main Street Intersection to just past 1st Street. City will provide engineering and construction management. *City public works staff will upgrade two non-compliant ADA ramps at Main Street prior to the paving work. This is part of a two part funding request that includes chip sealing all of W. Broadway west of the overlay project.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |