City of McCleary's FY 2009 Sidewalk Maintenance Project
2-W-956(002)-1
2-W-956(002)-1
FY 2009 Sidewalk Maintenance Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $92,037
County: Grays Harbor | Legislative District: 24 | Project Length: 0.23 | TIB Engineer: Chris Langhoff | Last Payment Date: 12/09/2010
Project Information
Lead Agency | MCCLEARY |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 0108 |
Project Length | 0.23 mi. |
ADT | 4,000 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | Nick Bird |
Contact Email | nickb@cityofmccleary.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 12/09/2010 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/31/2008 | 02/04/2008 |
Bid Auth. Approval | 05/31/2008 | 02/04/2008 |
Construction Approval | 11/15/2009 | 11/19/2009 |
Project Closeout | 09/01/2010 | 12/03/2010 |
Audit Date | 12/09/2010 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 40,342 |
Right of Way | 0 | 0 |
Total Design | 0 | 40,342 |
Construction Engineering | 0 | 24,772 |
Construction Contract | 92,037 | 152,962 |
Other Construction | 0 | 0 |
Total Construction | 92,037 | 177,734 |
Total TIB Funding | 92,037 | 218,076 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MCCLEARY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
AARA FUNDS | 126,039 | 57.8% |
Total Local Funding | 126,039 | 57.8% |
Project Description
Reconstruction of existing 5' sidewalk and curb on south side of Simpson Avenue from 6th to 10th.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
Financial Issues Project Delay |
05/04/2009 | Costs are higher than originally expected. City is applying for stimulus funds. |