Region: Southwest | Legislative District: 18 | Length: 0.50 mi. | FY 2023 Urban Arterial Program (UAP) |
Existing ConditionsSE Grace Avenue is the main north/south corridor serving Battle Ground's industrial core. It connects with NE Grace Avenue via an offset intersection with E Main Street, causing significant delays, safety concerns including accidents, and has proven to hinder private investment in and around Battle Ground. This corridor provides a connection between Battle Ground Village and Old Town and the Community Center. The lack of sidewalks and bike lanes make for a dangerous connection between these areas. The existing road directly abuts an unsignalized railroad crossing. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 0 | 331,500 | 331,500 |
Right of Way | 500,000 | 1,044,500 | 1,544,500 |
Construction | 2,500,000 | 1,934,056 | 4,434,056 |
Project Totals | $3,000,000 | $3,310,056 | $6,310,056 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
47.5% | 52.5% | 15% |
The solution to the problem described above is to expand this corridor to the standard 3-lane section for a minor arterial including bike lanes and sidewalks. Additionally, realigning this leg so that it connects directly to NE Grace Avenue at E Main Street and signalizing the new intersection.