City of Bremerton
Bremerton Sidewalk Gap Improvements
Perry Ave - Holman Rd to Stone Way; W Arsenal Way - New Hope Cir to Marion St
TIB Award Amount
$148,000
Region: West   |   Legislative District: 26   |   Length: 1,060.00 ft. FY 2021 Sidewalk Program (SP)

Existing Conditions

There are currently no sidewalks on the west side of Perry Ave between Holman Road and Stone Way and on north side of W Arsenal Way between Marion Street and New Hope Circle. There is a need for this project as both of these locations are on the pedestrian routes to schools and transit routes which are highly trafficked areas. This project will also improve pedestrian safety in these corridors.

Project Funding

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 148,000 52,000 200,000
Project Totals $148,000 $52,000 $200,000

Local Match

TIB Participation Local Match Minimum Local Match
74.0% 26.0% 20%

Description of Improvements

The solution to this need, is to utilize city crews to construct new sidewalk and curb ramps. This would improve pedestrian mobility, safety, and sidewalk connectivity.