Region: East | Legislative District: 9 | Length: 125.00 ft. | FY 2023 Small City Sidewalk Program (SCSP) |
Existing ConditionsThere is a half block section of sidewalk missing connecting downtown Tekoa to adjacent residential areas. Without this connection non vehicular traffic must traverse a rocky ungraded shoulder. The path is not ADA compliant and the existing sidewalk features two ramps that are also not ADA compliant. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 10,095 | 0 | 10,095 |
Right of Way | 0 | 0 | 0 |
Construction | 77,395 | 0 | 77,395 |
Project Totals | $87,490 | $0 | $87,490 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
100.0% | 0.0% | 0% |
Construct a short 125 ft section of sidewalk, replacing two existing ADA ramps with a single two way ramp and installing two one way ramps a much more accessible route can be provided for non vehicular travel.