Region: West | Legislative District: 24 | Length: 914.00 ft. | FY 2021 Small City Sidewalk Program (SCSP) |
Existing ConditionsThe project will improve the connectivity of pedestrian traffic from residential and commercial areas to the Junior High School and High School located on the south side of A Street SE. It will also improve access to the United States Post Office located on the northeast corner of A Street SE and Spartan Ave and the veterans services located on the southside of A Street SE. The project will complete the pedestrian facilities along the north side of A street SE and S. Blackberry Ave (westside of road). Pedestrian ramps will be brought up to current ADA standards. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 38,683 | 2,036 | 40,719 |
Right of Way | 0 | 0 | 0 |
Construction | 296,570 | 15,609 | 312,179 |
Project Totals | $335,253 | $17,645 | $352,898 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
95.0% | 5.0% | 5% |
This project proposes to construct approximately 914 feet of sidewalk, ADA ramps, curb gutter and HMA repairs along new curb line for the following streets: Spartan Avenue between E. Division Street. A Street SE between Spartan Ave and S. Blackberry Ave. S. Blackberry Ave. between A Street SE and E. Division Street.