City of Gold Bar
2022 Overlay Award
Multiple Locations
TIB Award Amount
$405,131
Region: Puget Sound   |   Legislative District: 39   |   Length: 0.00 mi. FY 2024 Small City Preservation Program (SCPP)

Existing Conditions

Anticipated Project Costs

  TIB Funds Local Funds Total Costs
Design 57,876 3,014 60,890
Right of Way 0 0 0
Construction 347,255 18,085 365,340
Project Totals $405,131 $21,099 $426,230

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 5%

Description of Improvements

This project grinds and provides a 2-inch overlay of the follow segments: 1st Aveune W from 1st St to Smeltzer Rd 415th Aveune SE from SR 2 to 419th Ave SE Dorman Road From SR 2 to BNSF Railroad Tracks