Town of Reardan
2021 Overlay
Multiple Locations
TIB Award Amount
$106,096
Region: East   |   Legislative District: 13   |   Length: 0.00 mi. FY 2023 Small City Preservation Program (SCPP)

Existing Conditions

Anticipated Project Costs

  TIB Funds Local Funds Total Costs
Design 7,717 0 7,717
Right of Way 0 0 0
Construction 98,379 0 98,379
Project Totals $106,096 $0 $106,096

Local Match

TIB Participation Local Match Minimum Local Match
100.0% 0.0% 0%

Description of Improvements

Project will patch potholes, crack seal, apply HMA pre-level and 1.5 HMA overlay, and shoulder rock. Water line is locate in west gravel shoulder and is not under road. 2 ADA ramps on Birch St are not compliant and will be replaced.